Question from Agile Release Planning
Using the following information find out how many iterations will be needed to complete the release.
The team has 300 story points worth of functionality left in the backlog to deliver in this release. The team’s velocity is quite stable averaging 30 points per iterations. However, in each iteration, they have been discovering 10% more work than anticipated, consist of change requests and new functionality. The product owner would like to know how many more iterations require to complete the release.