Showing only one result Read More Engr. Jamal Ahmed Khandaker, PMP Project Planning, Scheduling and Control by Primavera P6 Teacher Engr. Jamal Ahmed Khandaker, PMP Students 0 Engr. Jamal Ahmed Khandaker, PMP Review Students 0 ৳ 10,000.00 Learning Objectives Learning Project Management basic concepts Learn using Primavera P6 for Project Management Creating Project Scheduling and Budget … ৳ 10,000.00 Read More
Comments
Bhaia,
I am interested to join this session on 17 Feb’21.
Thanks
Iqbal Mahmud
Please just click on the BOOK NOW button, you will automatically be enrolled for the event. Thanks.
Dear Reza Bhai,
I would like to join this session on 15th Feb’21. Please enroll my name.
Thanks
Iqbal Mahmud
Total storypoint with extra work = (300 + 300* 10%) = 330
Team velocity per iteration = 30
No of iteration required = 330 / 30 = 11
Your answer is correct. Thank you.
11
Your answer is correct. Thank you.
(300+300*10%)/30=11
Your answer is correct. Thank you for the effort.